How to Review a Project with Net Present Value
By Prince Yadav, Founder & Lead Developer.
Why future cash flows are discounted
Money received later is not directly comparable with money received today. Discounting translates future cash flows into present-value terms using a selected rate.
List cash flows by period
Include the initial outlay and the expected later inflows and outflows at their correct times. Omitting maintenance, working capital, or end-of-project costs can make the result misleading.
Choose a defensible discount rate
The rate should reflect the purpose of the analysis and relevant risk or financing assumptions. A small change in the rate can materially change the present value of distant cash flows.
Read positive and negative NPV
Under the assumptions entered, positive NPV means discounted inflows exceed discounted outflows; negative NPV means the reverse. This is not a guarantee that the forecast cash flows will occur.
Test more than one scenario
Try lower revenue, higher costs, a delay, and a different discount rate. Scenario analysis helps reveal whether the decision depends on a narrow set of optimistic assumptions.
Avoid false precision
Forecasts are uncertain, and different projects may have different risks or strategic value. Use NPV as one decision tool and document the assumptions behind the inputs.
Why the discount rate changes NPV
Suppose a project costs ₹10,000 today and is expected to return ₹6,000 at the end of each of the next two years. At a 10% annual discount rate, the present value of the inflows is ₹6,000/1.10 + ₹6,000/(1.10²), or about ₹10,413. The NPV is therefore about ₹413 after subtracting the ₹10,000 initial cost. At a higher discount rate, those future inflows are worth less today.
The discount rate should reflect the decision context, timing, and risk assumptions rather than being selected simply to make NPV positive. Check that cash flows and rate use consistent periods, and that nominal cash flows are paired with a nominal rate (or real with real). Include relevant later costs and avoid counting the same cost twice.
NPV is a scenario result based on estimates, not a guarantee that a project will earn the forecast cash flows.
Sources and further reading
Related Calculators
Try the Calculator
Test the worked-example inputs in NPV Calculator, then change one input to see how the result responds.